Please follow the link below to review 360 Closure Communication 24-01, which summarizes an important regulatory update from the AER on the Conditional Adjustment of Reclamation Liability (CARL) Program.
Development of Site-Specific Guidelines & Remedial Action Plan (RAP)
Working closely with a developer, the City planning group, the AER, and the oil and gas licensee, 360 evaluated and remediated a contaminated site within the City of Edmonton that was slated for future residential development. Subject matter experts from 360 delineated the site extensively over 3 years and created an advanced environmental model that reduced the excavation volumes while saving our Client >$3 MM. Subsequently, the site fully meets environmental guidelines, and our client’s bottom line was protected.